Status of Pal Grden 89, Faridabad as below:-

* Active Construction work at Pal Greens, Sector-78, Faridabad will commence by 30th September 2010.
Excavation is Completed,Foundation laying B, E, F, G, H and I, Foundation Completion A, D and J , 2nd Floor Slab
C & D, Tower Status A Lower Basement Coloumn work completed and slab work in Progress,
B Raft work in Progress,C 3rd Floor Coloumn in Progress,D 2nd Floor Slab Casted & 3rd Floor Coloumn work in Progress
E Excavation and PCC Completed,F Excavation and PCC Completed,G Excavation and PCC Completed,H Excavation and PCC Completed,
I Raft work in Progress,J Upper Basement Coloumn work Completed & Slab Work under Progress.

Complainant's Goal: to satisfy the customer
Complainant's Target: Real estate business
Complaint Location: IndiaHaryanaGurgaon
Would you like to Comment on this Complaint?
By clicking "Post Comment" button, you agree to our Terms of Services and Privacy Policy
Recent Comments
1.
Wed, 06 Apr 2011  suresh

Dear Pal Victims (06/04/2011),

I want to caution everyone not to fall in the trap laid by pal builder and their claims about the projects getting started. Their only intention is to cheat the people and are in the process to show some construction to again take the money from the trapped victims.
They are not making any refund to people and their cheques are getting bounced.
Even if they ask for money do not pay at any cost and do not fall into their tactics if they ask you to shift to another project and pay the money.
Already lot of cases are in the court and day is not far when all these fraudsters Shagun Bhagat, Manav Chandra ,Harpal singh will be under the bars.
The day will come when these fraudsters and their families will repent the comforts enjoyed by them by looting the people’s hard earned money.